Section 8 - Erection By Others
Not The Responsibility Of The Company
8.1 ERECTION
8.1.1 The erection of the building system shall
be in accordance with the appropriate erection drawings, erection
guides and/or other documents furnished by manufacturer. It shall
be the erector's responsibility to comply with all appropriate
legal and safety requirements. It shall be the erector's
responsibility to determine and provide any and all temporary
bracing, shoring, blocking, bridging, and/or securing of
components, etc., as required during erection of the
building.
8.1.2 The Company is not responsible for
erection.
8.1.3 Upon request, the Manufacturer or its
Marketing Service may supply the name(s) of potential contractors
to install concrete and erect the building components or to perform
other work pertaining to the installation and erection of the
building components. Buyer acknowledges that neither the
Manufacturer nor its Marketing Service have investigated such
contractors, and that the provision of the name(s) does not
constitute a recommendation of the skill or competence of any
contractor. Buyer agrees to rely solely on his own investigation of
such matters when selecting contractor. The Manufacturer and its
Marketing Service are not involved in construction; any
representation or agreement between Dealer or Contractor and Buyer
concerning delivery, construction, modifications or other items are
between the parties thereto, and do not bind the Manufacturer or
its Marketing Service in any way.
8.2. FIELD MODIFICATION
8.2.1 Field design modifications will not be made
to any structural member except as authorized and specified by the
building manufacturer and approved and certified by the
Manufacturer's Engineer.